Disable your ad blocker to enjoy the full interactive features of this document.
Research
BARRIERS TO NET-ZERO SUCCESS
Lack of finance
Results of the survey point to councils being behind on meeting net-zero targets.
While some would suggest that the targets were unrealistic in the first place, a common refrain across the interviews was that lack of funding was hampering progress on net zero, particularly across counties and district councils. It meant there was pressure to make choices that would provide the best return on investment.
Funding failing to keep pace with inflationary costs, combined with exploding demand for child protection, adult social care and homelessness services, is taking its toll on net zero efforts. In early December 2023 Nottingham City Council became the fourth authority in the past 12 months – and the eighth in six years – to effectively declare insolvency. A Local Government Association survey found that one in five council chiefs believe it is “fairly or very likely” that they will go bust in the next 15 months.
Against this backdrop, results of the survey pointing to funding problems impacting on net zero were to be expected: 81% of respondents scored ‘financing as a barrier to decarbonisation’ as four out of five, where five is a considerable barrier. There was little confidence either that funding will be forthcoming from government to deliver net zero. When asked the question, ‘how confident are you that government will provide local authorities with sufficient funding to deliver net- zero?’, 89% answered not confident at all (one out five) with another 8% scoring it two out of five.
The cost of going net zero is enormous. One local authority, for example, said that they had spent £30 million on decarbonising (including government grants) which had reduced carbon dioxide emissions by 6%. A city council officer estimated the cost of decarbonising council functions by 2037 at £8 billion and said they would not be surprised if that figure eventually rose to as much as £10 billion.
As a consequence, two thirds (66%) said that it would be necessary to raise council tax to deliver net zero, even though they could not see this happening. As one interviewee put it: “The councillors won't stay in office very long if they're putting up council taxes at the current time and because we've lost a bit more government money we've got to save several million pounds.”
Environment leaders within councils highlighted how difficult it had become to get decarbonisation funding internally: “Just saying this money is needed for a carbon saving project is not good enough anymore, you need to show that there are accompanying additional benefits."
One interviewee commented: “I think it's important to explore those anyway and start talking about the potential health savings of cleaner air and things like that. But if you want to get a scheme funded, you have to frame it in terms of saving the authority money somewhere else.”
Though there was support from interviewees for decarbonisation funding from government through the Public Sector Decarbonisation Fund, there was a genuine weariness of the constant need to keep competing for funds which was time consuming and resource hungry. The funds are opened up in waves and bidders have to be quick off the mark to get them.
Others pointed out that the Social Housing Decarbonisation Fund required matched funding from those bidding, which put it out of reach of some councils and social housing providers.
Other difficulties with the scheme were also raised, including the tight timeframe in which the funding had to be spent.
Christopher Hammond, chief executive of UK100 – a network of climate-conscious councils - says the relationship between national and local government on net zero will need to change. “Local authorities have had 12 years of seeing their resources shrinking and shrinking. They've had to deal with a pandemic, they've had to deal with Brexit, and mounting social care issues. So there isn't a lot of money swirling around the system to then take on the big decarbonisation challenges.
“But the good news is that recent research shows that for every pound that you invest in local climate action, communities can reap up to about £14 worth of benefits, whether that's social, economic, or health benefits. So the cost of not doing this is going to be more significant than the cost of us planning for net zero.”
Hammond is convinced that funding has to be a mixture of public and private – a view shared by those local authorities interviewed. He says: “If we see decarbonisation as absolutely integral to our economic strategy and our industrial policy, then I think the country can get behind it.
“But we need a change in the settlement between local government and national government, because we can't just rely on council tax for these things.”
Lack of a statutory duty
It was clear from those authorities interviewed for the report that having a statutory duty to meet net-zero targets would help drive the issue up to the top of council’s priority lists. Though there is no shortage of will and good intensions, net-zero efforts play second fiddle to statutory duties such as homelessness and social care. Any change in the situation seems unlikely in the short-term, however.
The Independent Review on Net Zero (the "Skidmore Review") published in September 2022 recommended that the government should introduce a “statutory duty for local authorities to take account of the UK’s net-zero targets”. The government responded that it would not impose statutory targets on local authorities because there was “already a high level of local commitment” to the net-zero target.
With regard to the targets that have been set, our local authority interviewees spoke of a lack of clarity as to their roles. There is a clamour from local authority interviewees for greater definition generally in roles relating to net zero, which as they say, is largely voluntary. This ambiguity was picked up in an National Audit Office (NAO) report in July 2021, Local government and net zero in England. It said: “Central government has not provided local authorities with clarity about their roles in achieving net zero by 2050, and its approach to funding their net zero work is piecemeal.”
It continued: “Without a clear sense of responsibilities and priorities, there is a risk that local authority action on net zero is not as co-ordinated, targeted, or widespread as it might need to be.”
Carolyn McKenzie, director for environment at Surrey County Council, says: “It would be really beneficial to have a clear mandate on climate change, in the way we have on flooding. For flooding, we are the lead local flood authority, which means we bring together the data and action planning and convene the partnerships. We could do with something like that on climate change.”
Others point out that government “is unlikely to make it a mandatory duty as it is probably happy with the way things are – heavily hinting that it’s something we should be doing, but without actually making it statutory, therefore unfunded.”
Connection problems
Interviewees were asked: ‘Thinking about the planning and delivery of energy capacity, to what extent had your authority faced challenges securing new connections?’ On a score of 1 to 5, the average score was 4.17, where five represents considerable challenges. Half of those responding scored their answer as a five and 69% four or five. Asked where the challenges arise, 81% were cited as being down to electricity, with the remaining 19% having problems with electricity and gas.
This degree of concern and frustration, and the extended waiting times they were told to expect for a new connection, was reflected across many of the interviews. For some councils it was driving a coach and horses through their decarbonisation plans, particularly around solar power developments and even heat pump installation on larger buildings.
A comment by Melania Tarquino from Surrey County Council was not untypical: “We have quite a few projects to do solar farms on council land and for the last year we have been trying to find out when we can connect those projects to the grid. The response we are given is that there is a constraint imposed on a national level by National Grid that wouldn't allow us to connect any project bigger than 1MGW before 2037.”
“The reality is that in our Southern licence area, National Grid will come back to us and say if you want the megawatts it’s subject to reinforcement works and the earliest date that works will be undertaken at the moment is 2037 for some of our grid supply points. That is unacceptable but at the moment that is the situation.”
Austen Toone, SSE lead relationship manager for connections
Responding to the comments, SSE’s lead relationship manager for connections Austen Toone says all DNOs are mindful of the need to tackle the queue for grid connections but stresses the need for a collaborative approach.
He says: “We are regulated businesses and we have to follow the processes that are set out – and that is currently on a first-come, first-served basis. That means that if a data centre comes to us and has applied before a hospital that needs its power, we have to prioritise the data centre, as they are first in the queue, even if they’re not shovel ready. That means the data centre can potentially hold that capacity, preventing the hospital from connecting. We have to ensure we manage this queue as best as possible and that requires a collaborative approach across industry.”
He adds: “The reality of the situation is that it’s about communication, collaboration and transparency of data.
“One of the key issues is the planning of projects. We don’t get consulted at the earliest stage and if you’re applying for over 1MVA we have to submit a transmission impact assessment report. That can take up to three months to come back to us with an indicative date and a further nine months for confirmation.
“The reality is that in our Southern licence area, National Grid will come back to us and say if you want the megawatts it’s subject to reinforcement works and the earliest date that works will be undertaken at the moment is 2037 for some of our grid supply points. That is unacceptable but at the moment that is the situation.
“There’s work going on to reform the process and bring those dates forward to achieve net zero. But in the meantime, we urge councils to engage with us as early as possible.”
He adds: “But we are making some progress. Just before Christmas, we became the first network operator to provide revised offers to customers whose connections we are able to bring forward because we’ve released new capacity on the network. We’re going into 2024 discussing the terms of these connections in detail with our customers.”
Interviewees including Daire Casey, energy manager from West Sussex County Council, welcome the fact Ofgem is introducing new rules allowing National Grid's electricity system operator (ESO), which administers grid connections, to remove so-called zombie projects from the queue, while fast-tracking ones ready to go. “As a council we have been offered a grid connection for 2037, which is just absolutely bonkers.”
But the situation has also opened up the debate around whether more investment should be allowed in the price controls ahead of need.
Andrew Clark, business leader – place, at Energy Systems Catapult comments: “Obviously local authorities don't want to have to wait for connections and feel that more infrastructure should be in place ahead of ahead of exact need.”
This is pushed back by the regulator, who wants to keep costs down and does not want to give funding for infrastructure that might not be needed.
Clark says that the government’s response to the Winser Review is a positive development. Ministers have largely accepted the review’s recommendations setting out a package of reforms to halve the time it takes to deploy new electricity transmission infrastructure.
Government hopes a new Connections Action Plan along with bill discounts and wider ‘community benefits’ for those living near transmission infrastructure will prevent grid capacity and connections being a barrier to the clean energy rollout. More widely, government has now committed to long-term ‘whole system’ planning of network infrastructure coordinated by the National Energy System Operator (previously referred to as the Future System Operator), which is due to be established in Summer 2024.
in association with